Meeting Your Hydro Power Needs – Step 1 of 12

Jun 10
2009

When it comes to hydropower one of the first steps in hydro site evaluation is to perform a site energy survey.  Basically regardless of whether its small or micro hydro the power, a needs survey will help you to tell just how much value there is for the hydro electric energy potential that your site has.

Generally, the Micro Hydro sites will be easier to evaluate since more is known about the site power usage.  A simple checklist of power loads and maximum wattage will suffice to get the initial data.

For Small Hydro sites that plan to export power to the grid, you will need quite a bit more information about grid interconnects and local vs. remote loads, energy price structures and various generation vs. transmission charges associated with commercial power. Frankly this part of project evaluation can be quite intimidating for some energy markets.  Let us know if you need help performing this type of survey and we’ll see what can be done.

Regardless of hydro system size, keep your focus on answering the following question; “What is the market going to pay for this power?”  Later you will need to evaluate “What is the power generation going to cost?”

For a simple appliance load calculation form see ABS Alaskan’s:  Simple Energy Survey Form
Note:  This application does not save data, so fill it and print it out.

One problem with energy surveys is getting a handle on peak power usage. This peak energy need will determine the required maximum hydro generator or battery-inverter capacity. It can be tempting to simply take the sum of all devices and use that for power estimation, don’t do it.  In reality the overall system load capacity will limit out at the maximum rating for the home, farm or cabin’s maximum service panel rating (the big breaker or fuse feeding the whole system.)

Also, it may be worthwhile to count Heating loads as fed by gas or other sources since these can require much larger peak energy loads than is practical.   Hint: Hydropower Load dumps can supply part of this stored heat for a more system savings.

These calculations are designed to compensate for battery inverter conversion losses. Remember your system may have a different conversion efficiency factor. Also remember the hydro turbine and power generator have their efficiency factors as well.

Post to Twitter Tweet This Post

12 Small & Micro Hydropower Topics for Discussion

May 14
2009

Great response to last week’s question regarding the most pressing issue you have in Small & Micro Hydro. See last week’s Small & Micro hydropower question post and comments here.

This weeks Small Hydro Question for You -

This week I have another Small & Micro hydropower question for you to consider and answer. The following list is a grouping of  ‘SmallHydro‘ blog topics regarding Small & Micro Hydroelectric site survey and development procedures. We will cover these more extensively during future SmallHydro.com blog posts.

Please let us know in the comments for this post if any of these topics are pressing issues for you right now, and in what order you would like to see them covered. That will give us an idea of the best priority order in which to cover these topics for you in more detail.

12 Small & Micro Hydropower Topics for Discussion:

  1. Power needs for your regional site area
  2. Hydraulic pressure measurement, Head measurement & estimation
  3. Stream flow or “Q” measurement & estimation
  4. Hydrology & Flow Duration Curve (FDC) creation
  5. Penstock, Power-house, channels, weirs, trash-racks, pipelines, power-lines, etc. (infrastructure)
  6. Power calculations from Q-flow & head to kW-hours
  7. Regulations and hydropower licensing issues
  8. Turbine & control choices, types and equipment sources
  9. Hydropower overall system engineering evaluation (including engineering resources)
  10. Financial ROI & $ risks
  11. Field site measurements & methods
  12. Hydropower integrated summary of project (planning & optimization of your hydro system design)

That about sums up the topic areas.  Now please let us know; What do you need for developing your Hydropower site or improving your understanding of Small & Micro Hydropower?

Sincerely,
Jess

Post to Twitter Tweet This Post

Hydropower Calculation Example in Metric (SI) & British (US) units

May 14
2009

Last week I received a request for a working example of  hydropower calculation procedures.  Along with that request was another question asking what the 1/11.8 factor meant when working with feet vs. the 9.800 factor using meters and kW .  The latter 9.800 factor was what that reader was familiar with.  Please bear with me, there is a lot of interesting math ahead!

I will deal with both of these requests and a little bit more about hydropower efficiency computations  in today’s SmallHydro.com blog post.

Part of the mystery hydro conversion factor issue stems from the different measurement units used (SI) or metric vs. (US) or British imperial units.  These units of length, volume and time all play a role in getting the “right” answer when computing Small & Micro hydro power.  Above all, memorize this relationship:

HydroPower = Efficiency x Pressure drop x Flow rate = η x (ρ · g · h) x Q

Another interesting note shown at the bottom of the chart is that when computing the sites turbine inlet hydrostatic pressure = (rho x g x h) the pressure coefficient value for (rho x g) is quite different for each measurement unit type. This coefficient varies with the inverse of the 4′th power of the length for a given unit, hence all the strange conversion factors, like 1/11.82 for (US- kW) and 9.807 for (SI-kW), etc.

Generally it is best to stick with a single unit standard when working these problems to avoid mistakes! Metric really makes the conversion factors simpler, but the US is still using the British imperial system long after others have moved on, so I include it for comparison. Of interest too is that this site is right on the edge of Small or Micro Hydropower qualification.  It would make a nice renewable hydro power addition to a ranch, small village or community.

This handy chart shows an example of a 150 meter hydropower site with 0.095 cubic meters per second flow rate. The British (US) unit equivalents of 492.126 ft and 3.355 CFS are shown computed as well as incorporating both turbine and generator efficiency for accuracy.

Here is a PDF file of the same chart for printout: Hydropower-calculations-metric-si-british-us

Sincerely,
Jess

Hydropower Calculation Example SI & US units

Hydropower Calculation Example SI & US units

Post to Twitter Tweet This Post

What’s on Your Mind Regarding Small & Micro Hydropower?

May 07
2009

What are the essential one or two most important things that are blocking you from moving forward with your Hydropower site ideas or plans?

Now is your chance to pipe up about what is the biggest thing you think is preventing you from starting or completing your Small or Micro Hydroelectric project?

For example:  I’m blocked by; ‘Regulations…’, ‘Cash or capital issues…’, ‘Understanding the site…’, ‘Not sure how to proceed with…’, etc. You fill in the missing words in your comment on this post,  Try to keep discussion focused on the  issue that most impacts your progress.

Use the comments on this post to gain or give insight and provide feedback between all the readers.

This is also where a few of our more experienced Renewable Hydropower readers can really help by adding your comments to any threads as you have insight..

Sincerely,
Jess

PS.  This is a great time to think hard about what is really blocking your way forward with hydropower.

Post to Twitter Tweet This Post

SmallHydro

September 2010
M T W T F S S
« Dec    
 12345
6789101112
13141516171819
20212223242526
27282930  

Hydro Prospector Jess

Got SmallHydro?sidebar-pic
How may we help you Prospect for Small & Micro Hydropower Resources?

Twitter links powered by Tweet This v1.6.1, a WordPress plugin for Twitter.